buildingSMART Norway's Responsibilities:
- Work with EPM to ensure ongoing support on EDM Server
- Complete user management code (4 days)
- Complete EXPRESS for remaining methods (depends on EPM solving outstanding issue) (5 days)
- Complete java code, clean up and comment (7 days)
- Complete documentation site (3 days)
- Complete "Getting started" documentation, with links to online collaboration tools, etc. (3 days)
- Handle incoming support requests (3 days, rough estimate)
- Make new IFD browser look good (3 days)
- Publish new IFD Browser (1 day)
STABU's Responsibilities:
(Ideally completed by Washington DC milestone.)
- Design test for each method and user scenario
- Complete tests
- Fix code to ensure correct tests
- Design performance tests
- Run performance tests
- Work with EPM to resolve performance issues
- Add and harmonize LexiCon content
- Complete PSet tool, using Jakob Beetz and Håvard Bell
- Colaborate with Yoshi, Thomas and Nick